EV charger installation in the UK
An EV charger installation starts with a check of your home's electrical supply and earthing. Your installer works out when to notify the network operator and fits the chargepoint. Ask your installer to show you the smart settings. If you plan to use a grant, check eligibility before arranging any fitting work.
- Your installer checks the supply and earthing before fitting.
- The network operator must be told. The survey helps determine when.
- In England, ask who will notify any new circuit work and what certificate you'll receive.
Register your interest in EV charger installation with Padly.
What happens, step by step
- Check the grant route before booking work. If you might qualify, get any permissions you need and choose an OZEV-authorised installer and eligible chargepoint. Get a quote for the application. Don't let the fitting go ahead while you're waiting for OZEV to confirm you're eligible.
- Have the supply assessed. Your installer checks the capacity of the existing supply and the earthing. Show them where you park and where you'd like the chargepoint. Ask them to explain which work they can quote for and what still needs checking.
- Find out when the network operator needs to hear. The Distribution Network Operator, or DNO, must be notified for an existing property. Where the maximum demand including the chargepoint is no more than 60A per phase and the connection is known to be adequate, the installer can notify it within 28 days after fitting. In other cases, including where the property has a looped supply, the installer must contact the DNO before fitting.
- Fit, test and sort out the paperwork. Have the installer show you how they test the chargepoint and explain the sign-off. A home charger usually needs a new circuit. In England that work is notifiable under Part P. An installer registered with a competent person scheme authorised for this work can self-certify. If they do, they'll give you a certificate within 8 weeks of completion. Otherwise, the work needs to be notified to building control.
- Set up smart charging. Ask the installer to show you the user controls or app, including how to change the schedule. In Great Britain, private chargepoints sold for home or workplace use must meet the Smart Charge Points Regulations 2021. Chargepoints covered by the default-hours requirement come with off-peak hours already set. The requirement doesn't apply to chargepoints sold with a demand-side response (DSR) agreement. You can accept, change or remove the default hours, and override the schedule when you need to.
What your home needs
Start where the car actually parks, rather than where a charger would look neatest on the wall. A standard home smart chargepoint needs off-street parking. If you have no drive or garage, ask your local authority about permission for a cable gully before assuming you can run a cable to the street.
- Show the installer the parking space and the wall where you'd like the unit. Ask them to walk you through the proposed cable run.
- Point out the consumer unit and ask what the supply and earthing check means for the work they propose.
- Decide how you want to plug in. A tethered unit has its own cable attached. An untethered one has a socket and takes a cable you plug in yourself.
- Ask how the unit will connect to a network and where to check the Wi-Fi signal if needed. If you're choosing an EV or time-of-use tariff, check with your supplier about a smart meter. You'll typically need one for those tariffs.
If you've checked your parking and aren't applying for OZEV funding, you can Register your interest in an EV charger installation.
What changes the price
The Energy Saving Trust puts a typical installation at around £800 to £1,200. Use that as a budget marker, not a quote. Ask the fitter what they've allowed for the cable route and what the supply check means for the electrical work. Compare the description of the job as well as the total, particularly if an item is still to be confirmed after the survey. Our EV charger installation cost guide covers what to look for in the quote.
Home chargepoint grants
Renters and resident flat owners with eligible vehicles and a private off-street space they are legally entitled to use may qualify for up to £500. Get any required permissions from your landlord, freeholder or managing agent before applying. If you own and live in a house, you can't apply through the renters and flat owners route. A separate grant of up to £500 may be available if you own or rent and live in the property, only have on-street parking and are installing a cross-pavement solution such as a charging gully. Check which route applies in the gov.uk chargepoint grant guidance. The schemes run until 31 March 2027 and the government reserves the right to end or change them. Use an OZEV-authorised installer and an eligible chargepoint and wait for OZEV to confirm eligibility before fitting. Our EV charger grant guide explains the checks.
Choosing an installer
Ask who will assess the supply, contact the DNO and handle any building regulations notification. In England you can check registration on the Electrical Competent Person Register if the installer says they can self-certify. Ask what paperwork they'll leave with you so you know what to expect before you accept the quote.
Competent person registration and OZEV authorisation are separate checks. For a grant, use the authorised installer list on gov.uk. Padly offers connections with vetted and approved fitters. If you're relying on the grant, check that any installer you're considering is on OZEV's authorised list before you apply. For other home improvement topics, see the Padly guides hub.
Checked on 25 November 2026. Sources: gov.uk chargepoint grant guidance | OZEV renters and flat owners grant | gov.uk competent person scheme guidance | Energy Networks Association network guidance | gov.uk smart chargepoint regulations | Energy Saving Trust smart charging guidance, and Padly’s installer and enquiry information.
Frequently asked questions
Who tells the local electricity network operator?
Your installer can do it on your behalf. They check the supply first and establish whether the network operator needs to hear before the work or can be notified afterwards.
Can I fit the charger while OZEV reviews my application?
No. Wait until OZEV tells you that you're eligible. Getting an installer quote and submitting the application aren't the same as getting approval to proceed.
Will the charger stop working if it loses its network connection?
The smart chargepoint rules in Great Britain require covered devices to keep charging if the network connection is lost. They must also keep working if you switch electricity supplier.
Do I have to use the default charging hours?
No. If your chargepoint is covered by the default-hours requirement, you can accept, remove or change the default off-peak hours at first use or later. You can also override the schedule. The requirement doesn't apply to chargepoints sold with a demand-side response (DSR) agreement.
Who signs off the new circuit in England?
A registered competent person can self-certify notifiable work. Otherwise it needs to be notified to building control. Ask how the installer plans to handle it before accepting the quote.
What does tethered mean on a charger quote?
It means the chargepoint has a permanently attached cable. An untethered model has a socket, so you plug in your own cable.