Solar inverters: what they do and what to ask

A solar inverter converts the direct current (DC) electricity made by solar panels into alternating current (AC), which household appliances need. The Energy Saving Trust explains that conversion as part of a home solar system. When reviewing a quote, ask which inverter is proposed and why it suits the design.

At a glance
  • The inverter changes the panels’ DC electricity into AC for household appliances.
  • For inverter-connected generation, the inverter rating counts as the registered capacity.
  • The Energy Saving Trust says to expect inverter replacement after about 10 to 12 years.
  • Ask how any battery will connect and which network application route applies.

Get a solar quote

What an inverter does in a home solar system

Panels produce DC electricity. The inverter makes it usable by appliances that need AC. According to the Energy Networks Association (ENA), an inverter is needed to connect a generating unit with a DC output, such as solar PV, to an AC distribution network.

Its rating matters for the connection paperwork too. ENA’s G98 guide says that, for a power generating module connected through an inverter, the inverter rating is the module’s rating. That is the figure to look for on the quote and discuss with the installer.

Our guide to home solar panels gives a broader introduction before you compare quotes. For unfamiliar equipment terms, ask the fitter to show what each means on the proposed system drawing.

Types of inverter set-up

Microinverters

ENA describes microinverters as small inverters connected to small generating units, such as individual solar panels. This is often done so that if one panel is impaired, the output of the others is not affected. For your roof, the point to discuss is which panels the proposed arrangement connects to each microinverter.

The connection application is still based on the aggregate capacity of all generating units, rather than each small unit separately. For microinverters, that means the combined figure is the one to discuss with your installer.

Optimisers

The Energy Saving Trust says optimisers can help where shading is unavoidable. If one panel is shaded, it does not affect how much electricity the others generate. On an unshaded roof, optimisers will not help generate more electricity, but they provide extra opportunities to monitor performance.

Hybrid and dedicated battery inverters

MCS’s battery certificate guide records two connection types: AC connected with a dedicated inverter, or DC shared/hybrid inverter. Those are the descriptions to look for when comparing a proposed battery connection with the equipment on your quote.

The MCS guide also records whether the system is operable in island mode. If that matters to your plans, ask for a written explanation of the proposed equipment’s functions rather than assuming them from the word hybrid.

Shading, monitoring and the roof layout

ENA’s explanation of microinverters and the Energy Saving Trust’s advice on optimisers both address the effect of an impaired or shaded panel on other panels. Ask the installer to explain how the equipment addresses the shading on your roof.

For an unshaded roof, the Trust’s advice is specific: optimisers offer extra monitoring opportunities without increasing generation. If monitoring is the reason for including them in your quote, ask the installer to show what information you would see and how you would use it.

Some inverters have online monitoring and can warn you by email if the system fails, according to the Energy Saving Trust. The quote discussion is a chance to see what monitoring is included, what information it shows and what to do after a warning.

Why inverter ratings matter for G98 and G99

For a single premises in Great Britain, ENA’s G98 guide covers fully type tested generation connected at low voltage with total generating capacity up to and including 16 amps per phase. It equates that to 3.68kW on a single-phase supply at 230V, or 11.04kW on a three-phase supply at 400V. Above that aggregate-capacity threshold, G99 applies.

The guide covers Great Britain; ENA says Northern Ireland has different arrangements.

For inverter-connected generation, ENA says the inverter rating is the registered-capacity figure. The route therefore needs to be explained using that rating and your connection, rather than the number of panels alone.

For a qualifying G98 installation at a single premises, ENA says you do not need to contact the distribution network operator (DNO) before the equipment is running. The installer must inform the DNO within 28 days of commissioning using the Installation Document. All micro-generators connecting under G98 must be fully type tested.

GOV.UK describes the other route as apply to connect, with the installer submitting the application before installation. The installer must identify the applicable G99 application and any G100 export-limitation requirements described in ENA’s connection guidance. For apply-to-connect, the owner must ensure the DNO has granted authorisation before work starts.

GOV.UK says that, for low-voltage devices, the DNO will be in touch within 45 days to approve the installation or discuss amendments. That contact may therefore be a request for changes; it is not necessarily authorisation to start work.

ENA’s G98 Installation Document includes site and metering information, the owner’s contact details, generating capacity and the type test reference. It also includes installer accreditation and qualifications, supporting circuit diagrams and a signed compliance declaration. A copy of the submitted details gives you a record of what was declared for your system.

The Energy Saving Trust says the installer usually registers the system with the DNO. ENA says compliance is the customer’s responsibility, often the owner’s, and owners must ensure their equipment complies. Agree who submits the paperwork and ask for a copy for your records.

ENA’s LCT Register holds manufacturer declarations of compliance, and G98 equipment must have its declaration lodged there. Ask the installer to identify the proposed kit’s entry. Our solar installation guide explains the wider process.

Get a solar quote

Adding a battery now or later

For a battery now or later, the first question is whether the proposed inverter can take the battery you have in mind. MCS’s certificate descriptions distinguish DC shared/hybrid from AC connected with a dedicated battery inverter. Ask the installer which arrangement is proposed and what equipment would be retained or changed.

ENA says DNOs treat storage as demand when importing electricity and as generation when exporting. Storage must meet the relevant G98 or G99 requirements. With solar PV and storage together, G99 applies where the combined proposal exceeds the G98 aggregate-capacity limit or otherwise does not qualify for G98.

ENA’s connection guidance describes fast-track G99 procedures for eligible generation and storage proposals. Eligibility depends on the procedure, fully type tested inverters for all generating units including storage, aggregate-capacity limits and G100 export limitation where required. Ask the installer to confirm the applicable procedure, its conditions and timetable for your actual combination.

Our guide to solar battery storage covers the wider storage decision. The supplier’s treatment of battery exports is a separate question, covered in our Smart Export Guarantee guide. Both the connection route and the export terms belong in the discussion before you agree to the work.

Lifespan, warranty and replacement

The Energy Saving Trust says panels should last 25 years or more, while an inverter needs replacing after around 12 years. Its FAQ gives about 10 to 12 years for inverter replacement. MCS also says an inverter may need replacing during the panels’ life.

The Trust gives around £800 as an inverter replacement figure, depending on system size and manufacturer. For your own budget, ask for a replacement quote for the equipment you have. Our solar panel cost guide covers the wider installation budget.

Most inverters have a warranty of at least five years, according to the Trust, with extensions often available. It cautions that a 15-year warranty might cost almost as much as a replacement inverter. The extension price and written cover give you something concrete to compare with replacement.

MCS says the installer will provide a maintenance guide including common inverter signals and basic troubleshooting tips. The Energy Saving Trust says installers should leave written maintenance details including the main inverter fault signals. Ask the installer to explain those signals during handover and keep the guide accessible.

Questions to ask your installer

MCS encourages checking installer certification when getting a quote, before signing the contract and before installation begins, using its Find an Installer search. These questions give you specific points to discuss and record alongside the quote:

  • Which inverter type and rating have you proposed, and why does that suit this design?
  • Does G98 or G99 apply, who submits the documents, and what copies will I receive?
  • Can you show me the proposed equipment’s declaration on the ENA register?
  • What monitoring is included, and how will I recognise and report a fault signal?
  • How much would a warranty extension cost, and what does the cover include?
  • Where will you site the inverter, and why have you chosen that position?
  • Can this inverter take a battery later, and which connection route would apply?
  • Will you explain the maintenance guide and include the MCS certificate in the handover?

Checked on 26 November 2026. Sources: Energy Saving Trust solar, MCS solar PV, MCS battery certificate guide, ENA connecting generation, ENA G98 single premises guide, GOV.UK device registration.

Related Padly guides

Frequently asked questions

Why do solar panels need an inverter?

Solar panels generate DC electricity, while household appliances use AC electricity. An inverter converts DC to AC. ENA also explains that this conversion is needed when connecting a generating unit with a DC output to an AC distribution network.

When might a solar inverter need replacing?

The Energy Saving Trust gives about 10 to 12 years for inverter replacement. MCS says an inverter may need replacing during the panels’ life. Ask the installer about the proposed equipment’s likely lifespan and written warranty.

What should I budget for an inverter replacement?

The Energy Saving Trust gives around £800, depending on system size and manufacturer. That is a reference figure for budgeting. Ask for a replacement quote for your equipment alongside details of any existing warranty before agreeing to the work.

How is a microinverter used?

ENA describes small inverters connected to small generating units, such as individual panels. This is often done so that an impaired panel does not affect the others’ output. The connection application still uses the aggregate capacity of all units.

Are optimisers useful on an unshaded roof?

According to the Energy Saving Trust, optimisers will not help an unshaded roof generate more electricity, although they offer extra monitoring opportunities. Where shade is unavoidable, they can help prevent one shaded panel affecting the output of the others.

What does hybrid mean for a battery connection?

MCS’s battery certificate guide uses DC shared/hybrid inverter as one connection category. The alternative is AC connected with a dedicated inverter. Your installer can explain which arrangement is proposed and show the equipment involved.

Does inverter capacity affect the network application?

Yes. ENA says the inverter rating counts as registered capacity for inverter-connected generation. In Great Britain, G98 covers fully type tested generation connected at low voltage with total capacity at a single premises up to and including 16 amps per phase. Northern Ireland has different arrangements.

Will my existing inverter work with a new battery?

MCS records AC connections with a dedicated inverter and DC shared/hybrid connections. ENA says storage must meet G98 or G99 requirements. Ask an installer to assess the proposed combination and explain how adding the battery affects your network paperwork.