A combi heats water from the mains as you use it, so a combi boiler installation depends on your supply and hot water use. The job also includes any conversion work to remove a cylinder or loft tanks and, for gas combis in existing homes in England, the extra efficiency measure required by Boiler Plus.

At a glance
  • Ideal Heating recommends one shower at a time with a combi.
  • Several bathrooms or low water pressure may make a combi less suitable, according to Energy Saving Trust.
  • Worcester Bosch's conventional-to-combi conversion includes removing the loft water tank and cylinders, and will probably mean two days of labour.
  • In England, a gas combi in an existing dwelling should have at least one of four suitable efficiency measures under Approved Document L, paragraph 6.2.
  • Padly's listed combi installation starting prices ran from £1,699 to £2,907 including VAT, checked 27 November 2026. These are starting prices, not quotes.

You can Compare new boilers while you plan the work.

Is a combi right for your home?

Think about a normal morning at home. Does someone use a hot tap while the shower over the bath is running? A smaller household with little room for a cylinder may suit a combi, according to Energy Saving Trust. Several bathrooms, heavy hot water use or low water pressure may point towards a different choice.

One shower at a time is Ideal Heating's advice for a combi; it favours homes with a single bath or shower. Opening two or more hot taps causes a slight drop in temperature and pressure, the same guidance explains. Put that everyday pattern to the installer.

For the general explanation, see how combi boilers work and who they suit.

The figures below come from Ideal Heating's Logic Max Combi specification. Maximum hot water output and flow rate are separate measurements: only the flow rates are quoted at a 35°C temperature rise. Compare these model figures with your supply check.

Ideal Logic Max modelMaximum hot water outputFlow at 35°C rise
2424.2 kW9.9 litres/minute
3030.3 kW12.4 litres/minute
3535.3 kW14.5 litres/minute

Water pressure and flow checks before installation

A combi supplies hot water at mains pressure, as Worcester Bosch explains. If the pressure at home is already poor, mention it before settling on the boiler. Low water pressure may make a combi less suitable, according to Energy Saving Trust.

Have the installer explain the mains supply check alongside the proposed boiler's specification. What does the result mean for the bathroom shower and kitchen hot tap?

At handover, look for the recorded result for your installation. Hot water flow in litres per minute and a check of every hot water outlet are fields on HHIC's Benchmark checklist.

Converting from a regular or system boiler

In Worcester Bosch's conventional-to-combi description, the work includes draining the system, removing the old boiler, taking out tanks and cylinders, and changing pipework. The combi may go in a different position. Have the quote describe the changes proposed for your home.

The existing cylinder and any tanks need identifying in the proposed work. Worcester Bosch describes a conventional-to-combi conversion, so its removal list may not describe your system boiler conversion. Ask for the components included in your own job to be named in the quote.

The regular boiler guide and system boiler guide provide background for that discussion.

Show the installer your existing shower before agreeing to lose the cylinder. Existing showers should be examined for suitability when replacing a regular boiler and cylinder, Worcester Bosch advises, particularly pumped power showers designed for low pressure. Its guidance identifies mains pressure balanced and thermostatically controlled showers as compatible with combis.

An electric shower heats cold mains water itself and can provide hot water independently of the boiler, Ideal Heating explains. Have the installer identify what you've got.

There's a reason to pause before removing stored hot water if several people shower at once. A regular boiler's tank can serve that demand, according to Worcester Bosch. Talk through the household's use before choosing the conversion, including any plans for a heat pump later.

The Boiler Plus measure to agree in the quote

Get the extra efficiency measure written into the quote. In England, a gas combi fitted in an existing dwelling should have at least one suitable measure from the following list, under paragraph 6.2 of Approved Document L, Volume 1:

  • Flue gas heat recovery.
  • Weather compensation.
  • Load compensation.
  • A smart thermostat providing both automation and optimisation.

The names describe different ways of using heat or controlling the heating. With flue gas heat recovery, warmth that would leave in the exhaust is used to preheat the boiler's cold water supply, according to the government's Boiler Plus policy. Weather compensation varies the heating flow temperature with the outdoor temperature. Load compensation responds to the gap between the room's temperature and the setting you want.

A smart thermostat needs both automation and optimisation for this route, under the government Boiler Plus FAQs. Have the installer show which functions the proposed control provides and name the chosen measure in the quote. That gives you something specific to compare.

The guide to boiler controls and smart thermostat guide offer further reading before choosing the controls.

The boiler's efficiency matters as well as the extra measure. For gas boilers supplying central heating in existing dwellings, Approved Document L sets the usual minimum at 92% ErP; it also provides for exceptional circumstances. A room thermostat and timer are requirements for gas and oil heating under Boiler Plus. Compare the proposed controls alongside the appliance.

You can't choose to leave out the required measures to trim the job. The government's Boiler Plus clarification makes the standards mandatory and leaves compliance with the installer. They mustn't carry out a non-compliant installation, even at a customer's request.

For work booked ahead, check which edition and arrangements apply. Where the work isn't connected with higher-risk building work, 24 March 2027 marks the start of the 2026 edition of Approved Document L. It keeps the same four combi measures in paragraph 5.9.

Hard water, cleaning and protection

Cleaning belongs in the agreed work before the new boiler goes in. Central heating and primary hot water circuits should be thoroughly cleaned and flushed first, under Approved Document L. A suitable chemical inhibitor should be added to the primary heating circuit to protect against scale and corrosion. Domestic central heating preparation and commissioning should follow BS 7593.

A power flush, or a mains pressure flush for some models, is the Centre for Sustainable Energy's advice for clearing sludge and deposits. Ask the installer to explain which method is included in your quote.

If you're in a hard water area, discuss limescale treatment too. Suitable measures should treat feed water to water heaters and the combi's hot water circuit, according to Approved Document L. The hard water section of HHIC's Benchmark checklist asks about a scale reducer where the manufacturer requires one.

Use the boiler manual to discuss what the chosen manufacturer requires for your water supply. There's somewhere to record the work: HHIC's checklist has entries for the cleaner and inhibitor used, and whether a primary water system filter was installed.

If there's no magnetic filter, check that the replacement work includes one near the boiler, as Energy Saving Trust advises it should. Its advice also covers draining the heating system: whenever that happens, the inhibitor should be refreshed or replaced.

What happens on installation day?

Turn the engineer's Gas Safe ID card over to check the areas of gas work they're competent to do. The gas work must be done by a Gas Safe registered engineer competent in that area, as HSE explains.

These stages draw on Worcester Bosch's conversion description, the cleaning and commissioning guidance in Approved Document L, and HHIC's Benchmark checklist. Your agreed work should make clear which conversion tasks apply:

  1. Drain the system and remove the old boiler, as described in Worcester Bosch's conversion guidance.
  2. For a conventional-to-combi conversion, remove the applicable tanks and cylinder and change the pipework, following that Worcester Bosch description.
  3. Clean and flush before fitting the appliance. Suitable inhibitor should be added to the primary heating circuit, under Approved Document L.
  4. Fit the combi in the agreed position, which may change during a conversion, as Worcester Bosch notes.
  5. Commission the installation. Testing and adjustment should follow the manufacturer's instructions under Approved Document L; HHIC's Benchmark checklist records water flow and gas readings.
  6. Go through the boiler and controls with the installer. HHIC's Benchmark checklist includes demonstration, receipt of the manufacturer's literature and your signature confirming the handover.

A conventional-to-combi conversion will probably mean two days of labour, according to Worcester Bosch. Have the installer give you a timetable for your own job, with the removal and pipework changes included.

Keep the certificate in your paperwork folder. Where regulation 20 self-certification applies, the person doing the work must notify building control and give the occupier a certificate copy within 30 days of completion. The new boiler installation guide explains the wider paperwork trail.

You can keep the Benchmark record on your phone if that suits you. The latest version is digital and you can receive the completed record electronically, HHIC explains. Before handover ends, make sure you know where yours is and how to access it.

Check whether you'll be without heating or hot water and for how long. The CMA's consumer guide raises this planning question for green heating installations; it's also a useful question to put to your combi installer before booking.

The warranty registration is a separate check. Within one month of installation, the appliance needs registering with the manufacturer, HHIC says. The installer may do it, but responsibility for ensuring it's happened rests with you. Get confirmation rather than assuming the completed Benchmark record settles it.

Combi boiler installation costs

Use Padly's model prices as a starting point for comparison. The listings checked on 27 November 2026 showed installation starting prices of £1,699 at the lower end and £2,907 at the upper end, including VAT. These examples are listed starting prices; you'll still need a quote for your home:

A conversion needs its own description and price. Changing boiler type usually costs more than a like-for-like exchange because it involves different parts and procedures, Worcester Bosch explains. Compare what's included in the work as well as the boiler model, so you can query any differences between quotes.

For further price reading, use the combi boiler prices guide and new boiler cost guide.

Questions to ask before you book

At least three installer visits are recommended by Worcester Bosch, while Energy Saving Trust advises at least three quotes. Keep the same questions to hand when comparing them:

  • What does your supply check mean for the proposed model and the showers we use?
  • Which cylinder, tanks and pipework are included in the conversion work?
  • Which Boiler Plus measure is included, and why does it suit this system?
  • What cleaning, inhibitor, filter and hard-water treatment have you allowed for?
  • When will you demonstrate the controls and give me access to the completed Benchmark record?
  • Who handles building regulations notification and warranty registration, and how will I receive confirmation?

For wider background before those visits, return to the general combi boiler guide.

Padly is an introducer, so we don't fit boilers ourselves. You can visit Padly's boiler installations page or Compare new boilers.

Checked on 27 November 2026. Sources: Approved Document L Volume 1, 2021 edition (gov.uk) | Approved Document L 2026 (gov.uk) | Boiler Plus FAQs and policy document (gov.uk) | Energy Saving Trust, boilers | Ideal Heating, combi boilers and showers, Logic Max Combi specification | Worcester Bosch, changing from conventional to combi and combi shower FAQ, step-by-step installation | Benchmark and HHIC commissioning checklist and digital guidance | Building Regulations 2010, regulation 20 | HSE domestic gas FAQs | Centre for Sustainable Energy | CMA, buying green heating and insulation products consumer guide | Padly boiler model pages (prices checked 27 November 2026).

Related Padly guides

Frequently asked questions

How much time should I allow for fitting a combi?

Worcester Bosch's usual installation range is 1 to 3 days, with complexity affecting the time. Its guidance says most straightforward like-for-like swaps can be completed in a day, while conventional-to-combi work will probably mean two days of labour. Get a timetable for the work at your home before booking.

Should I plan to run two showers from a combi?

One shower at a time is Ideal Heating's recommendation for a combi. For several bathrooms used together, it favours a system or heat-only boiler. Explain who needs hot water at the same time during the installer visit, so the choice reflects your household's routine.

Is the smart thermostat route compulsory for a new combi?

No. For a gas combi in an existing dwelling in England, Approved Document L says at least one suitable measure should be fitted. Alternatives to a smart thermostat are flue gas heat recovery, weather compensation and load compensation. The smart option needs both automation and optimisation.

Can I keep a pumped power shower after conversion?

A power shower's built-in pump needs a hot water cylinder, which combis don't use, Ideal Heating explains. Before agreeing the conversion, ask the installer to assess your existing shower so the proposed work takes account of its compatibility with the new boiler.

Will the cylinder and loft tanks be taken out?

Tank and cylinder removal forms part of Worcester Bosch's conventional-to-combi description, alongside pipework changes. What that means at your home needs agreeing with the installer. Have the quote identify the existing cylinder and any tanks it includes, rather than relying on a general conversion description.

Must every combi have a water softener or scale reducer?

Treatment should reduce limescale in a combi's hot water circuit in hard water areas, according to Approved Document L. A scale reducer is conditional on the manufacturer's requirements in HHIC's Benchmark checklist. Check the boiler manual with the installer to establish what's required for your installation.

What is the lowest listed Padly combi installation price?

The Navien NCB300 Combi and one other listed model shared Padly's lowest listed combi installation starting price of £1,699 including VAT, checked on 27 November 2026. These are starting prices, not quotes. Your home's conversion work needs its own quote.

What should I discuss if a heat pump is planned later?