New boiler installation guide: what happens from quote to commissioning

For a new boiler installation that replaces an old one, this guide covers installer visits and written quotes, removal, cleaning and flushing, fitting and commissioning, then building regulations notification and warranty registration. Approved Document L says the system should be cleaned and flushed first. HSE requires anyone employed on domestic gas appliances to be Gas Safe registered and competent.

At a glance
  • Anyone employed on domestic gas appliances must be Gas Safe registered and competent in that work, under HSE's rule.
  • Where self-certification applies, regulation 20 requires a certificate copy for the occupier and notification to building control within 30 days of completion.
  • Before installation, heating and primary hot water circuits should be cleaned and flushed, and suitable inhibitor added to the primary heating circuit, under Approved Document L.
  • The engineer should complete the Benchmark checklist at installation; you should sign after a full, clear explanation of operation, according to Benchmark.
  • The boiler needs warranty registration with the manufacturer within one month of installation, according to HHIC.

Start with the boiler options: Compare new boilers.

Before installation: the survey and written quote

A home visit is your chance to explain how you use heating and hot water. Having at least three installers visit is Worcester Bosch's recommendation; it suggests discussing a similar replacement alongside any alternative arrangement. Getting at least three quotes is also advice from Energy Saving Trust and the Centre for Sustainable Energy.

The quote should cover power flushing, controls and system changes, according to Worcester Bosch's installation guidance. Its advice also identifies the boiler, system type and position in the home as factors in the overall cost. Ask what each proposal includes rather than comparing the boiler names alone.

Get the included work, exclusions, agreed total and timetable written down before accepting. The CMA's consumer guide for green heating and insulation products recommends these written details.

Will you be without heating or hot water, and for how long? Put that question to the installer and have the answer recorded with the timetable, adapting the CMA guide's advice about interruptions during work.

Choosing the boiler type and size

Describe your heating, shower and tap use at the survey and ask the installer to explain the proposed boiler type and output. Worcester Bosch recommends discussing heating and hot water needs during the home visit.

A combi may suit a smaller household using less hot water, while a system boiler may suit a larger family with higher demand, according to Energy Saving Trust. Its guidance flags low water pressure and several bathrooms as reasons a combi may be less suitable.

For the equipment choices, read the combi boiler guide or the system boiler guide.

Taking out the old boiler and cleaning the system

Replacing the boiler and changing the whole arrangement are different proposals. Draining the system and taking out the existing boiler are usual replacement tasks in Worcester Bosch's conversion guidance. For a conventional-to-combi change, it also describes removing tanks and cylinders, altering pipework and possibly moving the boiler. Ask which of those jobs your quote allows for, including what happens to any loft tanks.

Before the new appliance is installed, all central heating and primary hot water circuits should be thoroughly cleaned and flushed, under Approved Document L, paragraph 8.8. A suitable chemical inhibitor should be added to the primary heating circuit to protect against corrosion and scale. Preparation and commissioning should follow BS 7593.

A power flush is the Centre for Sustainable Energy's advice, with a mains pressure flush an option for some models. Ask the installer which method is proposed for your system.

If the heating system is drained for replacement or maintenance, inhibitor should be refreshed or replaced, according to Energy Saving Trust. Its guidance also advises fitting a magnetic filter near a replacement boiler where there isn't one already.

For its 800 range, Baxi makes fitting and maintaining the magnetic filter a warranty condition. Check that condition against the Baxi warranty offered with your quote.

At handover, look for the cleaner and inhibitor names and the entry showing whether a primary water system filter was installed. These fields are in the HHIC Benchmark checklist, so you can ask to see what was recorded for your job.

Flue, condensate and gas supply checks

Before accepting the proposal, ask about changes to the gas supply or pipework and where the flue would go. The boiler flue regulations guide can help you prepare that discussion.

You don't need to interpret the gas readings yourself. The HHIC checklist records the gas rate and burner operating pressure or gas inlet pressure, as applicable. For a condensing boiler, it also records whether the condensate drain follows the manufacturer's instructions and/or BS5546/BS6798. Ask the engineer to explain those entries when showing you the record.

Controls to agree with the installer

Agree the controls as part of the job. The Approved Document L and Boiler Plus provisions discussed here apply in England. With a replacement boiler, thermostatic room controls should be provided for each heated room under the 2021 Approved Document L guidance, allowing justified zones and cases where individual control isn't technically feasible.

Heating and hot water should have separate time controls unless they already share a single time controller, according to Approved Document L. A boiler interlock should also be installed. Controls should be wired so the boiler and pump switch off when neither heating nor hot water is needed.

For a gas combi in an existing dwelling, at least one appropriate additional measure should be installed under Approved Document L, paragraph 6.2. The choices are load compensation, weather compensation, flue gas heat recovery or a smart thermostat providing automation and optimisation. A smart thermostat only counts if it has both automation and optimisation, according to the Boiler Plus FAQs.

Customers can't opt out of the standards, and installers mustn't agree to a non-compliant installation, according to the government's Boiler Plus clarification. Read the guide to boiler controls and the combi installation guide before settling the proposal.

The room controls and additional combi measures are covered by the 2021 Approved Document L. For work not connected with higher-risk building work, the 2026 edition takes effect on 24 March 2027 and retains the same combi measure list.

Commissioning: the tests behind the Benchmark record

Commissioning means bringing the installed system into working order through tests and adjustments, in Approved Document L's terminology. Fixed building services must be commissioned so they use no more fuel and power than is reasonable. Testing and adjustment should follow the manufacturer's instructions.

The engineer should fully complete the Benchmark checklist at installation as a means of complying with building regulations in England and Wales, according to Benchmark. You can receive the completed record electronically: HHIC says the paper version is no longer maintained and the latest record is online or in the Benchmark apps.

Here are the details covered by the published HHIC checklist:

  • Heating and hot water controls, thermostatic radiator valves and boiler interlock.
  • Cleaning to BS7593 and the manufacturer's instructions, plus cleaner, inhibitor and filter entries.
  • Gas readings, heating flow and return temperatures, carbon monoxide readings and CO/CO2 ratios.
  • For a combi, hot water flow rate and confirmation of a hot water check at every outlet.
  • A demonstration of the boiler and controls, with the manufacturer's literature left for the customer.

By signing, you confirm you've had a full, clear explanation of how to operate the system, according to Benchmark. In Baxi's description, it confirms the demonstration and completed handover. Ask for anything you don't understand to be shown again before signing.

Gas Safe checks and building regulations notification

Check registration and the work categories on the back of the engineer's ID card before gas work starts. For paid work on a domestic gas appliance, the engineer must have Gas Safe registration and competence in that work, as HSE's domestic gas FAQs explain. They give the Gas Safe Register website or 0800 408 5500 for registration checks.

Installing or replacing heating may need approval, according to the GOV.UK building approval guidance. A competent person scheme member can self-certify and inform the local authority if needed, so you don't have to obtain approval yourself. For gas work, Gas Safe Register appears in the government's scheme directory.

Where self-certification applies, the installer has two duties within 30 days of completion under regulation 20: give the occupier a certificate copy and notify building control, using a notice or the certificate. For competent person scheme work, Approved Document L also requires the commissioning completion notice within 30 days.

Notification leads to a Building Regulations Compliance Certificate for the homeowner, according to Benchmark. Once it arrives, HHIC asks the customer to enter the notification number on the Benchmark checklist. Keep the certificate in your paperwork folder for a future sale, as Energy Saving Trust advises.

For the wider replacement decision, see the boiler replacement guide.

Padly is an introducer, so we don't fit boilers ourselves. You can visit Padly's boiler installations page or Compare new boilers.

Handover, warranty registration and annual servicing

Ask for a demonstration of the timers using the instructions you'll keep. Operating and maintenance instructions should explain the system's purpose, location, use and upkeep, under Approved Document L. They should cover timers and sensors, point you to the boiler manual and include a completed commissioning sheet where relevant.

Registration with the manufacturer is needed within one month of installation, according to HHIC. Your installer may submit it, but you're responsible for making sure it happens in time. Agree who'll do it before they leave.

For a Vaillant boiler, its guarantee terms set a 30-day registration deadline; missing it reduces the guarantee to 12 months from installation. Baxi also specifies 30 days. Under Baxi's terms, failure to meet registration, Benchmark or annual-service conditions makes its warranty revert to the standard one year.

An annual service is required to maintain Worcester Bosch's guarantee. Appliances need servicing at least annually in line with the manufacturer's recommendations, according to HHIC, with a Gas Safe registered engineer for gas boilers. It warns that failing to follow the manufacturer's servicing requirements is likely to invalidate the warranty.

Check the proposed manufacturer's conditions with the boiler warranty guide alongside you.

Paperwork after a new boiler installation

Use this list to check what you've received. Where the boiler changes but the pipework and radiators stay, the replacement components' energy performance should be assessed and recorded for you under Approved Document L, paragraph 9.8. Product data sheets are one permitted form of that record.

DocumentWhat it showsSource
Benchmark checklistTests, controls and handover record.Benchmark and HHIC
Building Regulations Compliance CertificateEvidence it complies, though not final proof; copy due within 30 days of the work finishing where the installer self-certifies.Reg 20; Benchmark
Operating instructions and commissioning sheetHow to use and maintain the system; the sheet where relevant.Approved Document L, 9.2
Manufacturer warranty registrationDue within one month of fitting.HHIC
Energy performance recordShould be recorded for you when the pipework and radiators stay; product data sheets are one permitted form.Approved Document L, 9.8

How long does installation take?

A usual installation takes 1 to 3 days in Worcester Bosch's guidance, with most straightforward like-for-like swaps possible in a day. Its conventional-to-combi guidance says the additional steps will probably mean two days of labour. Ask for a timetable for your particular proposal.

New boiler installation starting prices

Padly's listed installation starting prices, checked on 27 November 2026, were from £1,699 for combis, from £2,249 for system boilers and from £2,149 for regular boilers, including VAT. These are starting prices, not quotes for your job. Read the new boiler cost guide and boiler replacement cost guide when comparing what's included.

Questions to put to your installer

  • What makes this boiler suitable for our heating and hot water use?
  • Can you show me the exclusions in the written total?
  • Which cleaning method and water treatment does the proposal include?
  • How will the extra combi efficiency measure work with these controls?
  • Could you show me how to find my completed Benchmark record on my phone?
  • What confirmation will show that building control has been notified?

Checked on 27 November 2026. Sources: Approved Document L Volume 1, 2021 edition (gov.uk) | Approved Document L 2026 (gov.uk) | Boiler Plus FAQs (gov.uk) | HSE domestic gas FAQs | Building approval, gov.uk | Building Regulations 2010, regulation 20 | Benchmark, What is Benchmark | HHIC, Benchmark goes digital and commissioning checklist | Energy Saving Trust, boilers | Centre for Sustainable Energy | Worcester Bosch, step by step boiler installation | Vaillant and Baxi guarantee terms.

Related Padly guides

Frequently asked questions

Is a conversion the same job as replacing a similar boiler?

There's more to discuss than the boiler itself. In Worcester Bosch's conventional-to-combi guidance, the work also includes removing tanks and cylinders, changing pipework and possibly choosing a different boiler position. Ask which conversion tasks appear in your written proposal.

What should I check about the person doing the gas work?

Start with their Gas Safe ID card and the work categories on its back. For anyone employed on domestic gas appliances, registration and competence in that work are required by HSE. You can check registration through Gas Safe Register online or by telephone.

What changes if the installer can self-certify?

A competent person scheme member can inform the local authority if needed and give you a certificate, according to GOV.UK. You don't have to obtain approval yourself when using that route. Ask the installer to explain whether their scheme covers the proposed work.

Does signing the Benchmark record mean I've had a demonstration?

Your signature acknowledges a full, clear explanation of operation under Benchmark's guidance. It shouldn't be a box you tick while still unsure about the controls. Ask the engineer to go through anything you haven't understood before you sign.

Does cleaning always mean a power flush?

A power flush is advised by the Centre for Sustainable Energy, but its guidance allows a mains pressure flush for some models. Ask which method the installer proposes. Approved Document L says the central heating and primary hot water circuits should be cleaned and flushed before installation.

Can I leave warranty registration to the installer?

An installer may submit the registration, according to HHIC, but responsibility for making sure it's done in time remains with you. Agree who'll submit it and how you'll check completion, using the proposed manufacturer's conditions rather than assuming every warranty works alike.

Which installation records should stay accessible?

HHIC advises keeping access to your Benchmark record for servicing or a house move. For the building regulations certificate, Energy Saving Trust recommends keeping it safe for a future sale. Ask where your electronic record is held before the handover ends.

Can I ask to leave out the extra combi efficiency measure?

You can't opt out of the standards under the government's Boiler Plus clarification, and an installer must refuse a non-compliant installation even if you request it. Discuss the appropriate measure before accepting the proposal so you understand what's being included.

For your next step, Compare new boilers.